The French A837 tollway connects the Atlantic façade in la Rochelle to the Paris -Bordeaux main axis. Following the path of the Charente River, the road crosses a predominantly flat area near Rochefort with three marshlands identified as main sources for large amplitude settlements after fill placement:
- the Tonnay Charente marshland crossing 2 canals and with an average of 20 meters of compressible normally consolidated clay, divided in 3 distinct areas,
- the Boutonne river where a four arches bridge will require 7 meters height access embankments,
- the Agnet, consisting of a narrow 20 meters deep thalveg valley with alluvial deposits.
The objective of the Menard vacuum consolidation treatment (MVC), patented, was to enable fast construction of the road embankments and reduce post-construction settlement to within acceptable limits.
Although part of a private construction project, implementation of the MVC was closely monitored by the geotechnical section of the French Highway Authority (SCETE Bordeaux) as well as by an independent geotechnical consultant (SORES) for additional instrumentation and follow up.
Although the soil conditions were variable across the various sites, the subsoil generally consisted of soft, normally consolidated clay with the following characteristics:
|
Area |
Tonnay-Charente |
Boutonne |
Agnet |
|
Average depth (m) |
16.5 < Dave<22.1 |
8.3 < Dave<13.2 |
8.3 |
|
e0 (void ratio ) |
1.03 < e0 <2.22 |
1.5 |
1.88
< e0 <2.33 |
|
Cc ( compression index ) |
0.33 < Cc <1.24 |
0.30 < e0 < 0.8 |
0.99 < e0 <1.07 |
|
Cs ( recompression index ) |
0.035 < Cs < 0.079 |
0.035 < Cs < 0.08 |
0.07 < Cs < 0.08 |
|
Cae ( secondary consolidation) |
0.019 < Cae < 0.068 |
0.01 < Cae < 0.032 |
0.045 |
|
Ch (10-3cm2/sec) ( coefficient of horizontal consolidation ) [ ratio Ch / Cv = 7 ] |
3.9 < Ch< 7 |
1.4 |
2 |
|
Cu (kPa) |
17 < Cu[1] < 75 |
15 < Cu < 28 |
13 < Cu < 25 |
Table 1 : Design Soil parameters
The basic procedure of MVC consists in removing atmospheric pressure from a confined sealed medium of soil to be consolidated and maintain the vacuum during a pre-determined period of time as illustrated below.

Fig. 1
- Menard Vacuum system (MVC) typical cross-section
Technological problems associated with this method include:
The preliminary steps associated with the MVC design are summarized below (see table 1 for case history values):
During the consolidation period it is then necessary to calibrate the settlement objectives on the basis of the on-going vacuum parameters – see fig 2 for a description of a typical instrumentation profile:
§ check the actual depressurization level using vacuum gauges placed in the draining fill (below the membrane and above the water table)
§ record the on-going settlement at the surface (settlement sensors) at fixed time interval and use the Asaoka method to find out:
· the empirical final settlement value under the combined effect of (vacuum + full embankment height)
· the in-situ coefficient of radial consolidation Cr
§ compare the settlement targets and re-evaluate the consolidation rates objectives using a consolidation program
§ Monitor the settlement of the various layers using multi-point settlement gauges as shown on Fig 5.
|
Tollway section |
Tonnay Charente |
Boutonne |
Agnet |
|||
|
Area |
West Daurade |
Daurade RD 911 |
RD 911 St
Louis |
Right Bank |
Left Bank |
|
|
DESIGN DATA |
||||||
|
Road elevation above GL |
1.70m |
1.55m |
1.85m |
7.55m |
5.25m |
5.90m |
|
Computed 30years settlement, S30 |
2.56m |
1.80m |
1.55m |
2.10 m |
2.35m |
2.00m |
|
Total Height of Embankment |
4.26m |
3.35m |
3.40m |
9.35m |
7.57m |
7.90m |
|
Estimated settlement with vacuum, S∞,MVC |
3.75m |
3.02 |
1.88m |
2.30m |
2.50m |
2.43m |
|
Consolidation rate target, Uave% |
68% |
60% |
82% |
90% |
94% |
85% |
|
Vacuum transmission pipes grid (drainage) |
1.5m square grid |
1m square |
1m square |
1.35m square |
||
|
CONSTRUCTION
MONITORING |
||||||
|
Asaoka final settlement |
2.47m |
1.81m |
1.10 – 1.90m |
1.60m |
1.34m |
1.09m |
|
Achieved settlement |
2.18m |
1.65m |
1.10 – 1.80m |
1.52m |
1.15m |
1.03m |
|
Achieved consolidation rate
(PPG) |
69% |
75% |
67% |
- |
83% |
76% |
|
Achieved
settlement compared to calculation |
89% |
96% |
101 – 114% |
105% |
90% |
|
In addition to the previous measurements, pore-pressure gauges (PPG) placed in the sub-soil will record the evolution of pore-pressure dissipation during the consolidation process – see fig 3.
The PPG readings taken at different elevations can also be plotted on a pore-pressure vs. depth diagram, as on fig 4. The ratio of consolidation at a given time hence corresponds to the ratio of the area between line AD and the actual monitoring curve to the area defined by ABCD.
Finally, inclinometers are installed for qualitative interpretation. The fact that soil contraction occurs near the surface seems in accordance with the higher drainage characteristics nearer to the drainage platform. The values measured are relatively small – less than 100mm – as compared to what would have occurred during consolidation with only the embankment weight (the vacuum and the embankment weight tend to balance each other actions).
Fig 6 shows the long term expected settlement at 30 years based on post-construction settlement data on the Agnet area gathered from the end of the work until 2003 (2250 days). The slope of the settlement curve in log (t) coordinates indicate a secondary settlement in line with the initial expectations and the analysis of the settlement versus log t curve shows that a total settlement between 90 and 110 mm should be expected after 30 years of operation for the highway.
This paper highlighted the different quality control measures performed during a Menard vacuum job to monitor the consolidation process.
Further to the construction of the toll way, long term monitoring of road settlement have been generally satisfactory, with an average settlement of less than 100mm in the first 6 years.
Fig 2 : Typical Instrumentation Profile
Fig 3 : Typical Piezometer Readings versus time ( here Piezometer No CPI18G located at
elevation -3.95 NGF ) – Embankment height is also indicated for information
Fig 4 : Monitoring of Pore Pressure versus depth – Theoretical curves are dashed
Fig 5 : Typical Multidepth Settlement Gauge Reading -
Fig 6 : log10
( time ) - Residual Settlement after end of Vacuum Consolidation curve
(Red line is the linear regression based on last three points – green curve is linear regression
based on initial 8 points)
Tonnay Charente site during vacuum

Boutonne River site during vacuum