Cyril Plomteux, Ali Porbaha, and Charles Spaulding
ABSTRACT:A wide range of deep foundation systems
has recently been developed for construction of embankments on soft soils. Controlled Modulus Columns (CMC) is one
technique of ground modification, originally developed in
INTRODUCTION
Embankment construction is an essential element of any highway and railway construction. The problem arises when the embankment passes through soft ground conditions such as soft clay, bay mud, organic soil/peat, chalk or loose fine sand. In that case the soil is subject to settlement or stability problem due to lack of bearing capacity; and/or in case of loose saturated fine sand subject to liquefaction due to ground shaking. To overcome these difficulties, a wide range of deep foundation systems has recently been developed for construction of embankments on soft soils (Porbaha et al, 2002a and b). These techniques take advantages of various ground modification concepts such as densification, reinforcement, solidification, etc. (see Figure 1).
The objective of
this paper is to present a new deep foundation system, namely Controlled
Modulus Columns (CMC), for support of embankments. The detail of design,
construction, and monitoring of an embankment project supported by the CMC
system is outlined here.

Figure 1: Concept of column-supported embankment
Controlled Modulus Columns
The Controlled
Modulus Columns (CMC) is a ground modification system that reinforces soil by
screwing a hollow auger into the soft soil and installing a low-pressure
cement-based grout column through the hollow auger (see Figure 2). The combined
effect of densification and reinforcement improves characteristics of the soft
ground due to composite action. The
CMC system uses a displacement auger powered by equipment with very large
torque capacity and very high downward thrust, which displace the soil
laterally with virtually no spoil or vibration. The auger is screwed into the
soil to the required depth and as such it increases the density of the
surrounding soil and thus increases its load bearing capacity. When the
required depth or a preset drilling criteria (usually rotational torque) is
reached, a highly workable grout-cement mixture is pumped through the center of
the hollow auger. The grout mixture then flows under low pressure out of the
auger base as it is retracting to obtain a high capacity column that can be
used in close vicinity of sensitive structures. The grout is injected under low
pressure, typically less than 10 bars (145 psi) and no soil mixing takes place
during the pressure grouting. To ensure that the soil above the auger remains
compacted, the top of the auger is equipped with reverse direction flights. The
result is a composite system with column reinforcements bonded to the
surrounding soil. The main features of
CMC technology are:

Figure 2: CMC Foundation system (a) Construction process (b) CMC Rig
The case history of a project in which CMC foundation
system was used for embankment support is discussed here.
Project Description
The project consists of improving the ground under the access embankment
of a road crossing over the Channel Tunnel Rail Link (CTRL) covering 17
kilometers of railways construction. The embankment height ranged up to 7.5
meters and live load of 20 kPa from the road traffic was taken into account.
The main design requirement for the ground improvement was to limit the
post-construction settlement of the embankment to 10 mm per decade. The works
have been done in a design and built basis, using a Controlled Modulus Columns
solution.
Subsurface
Condition
The geotechnical data for this project is derived from the Cone
Penetration Tests (CPT’s) performed along the axis of the anticipated
embankment from station 0+420 to 0+600. The CPT results are presented in Figure
3.
A very soft alluvium layer, made of a succession of very soft clay (wp=60%,
wL=150%, 60%<w<150%) and fibrous peat (wL=480%,
250%<w<450%, Cu=33 kPa), was extending all over the site with
a variable thickness ranging from 11 m at station 0+420 to 6 m at station
0+600. In this alluvium layer, CPT cone resistance values qc were
less than 0.5 MPa with typical values around 0.3 MPa. Under this very soft
alluvium layer was a medium density structureless chalk layer with silt
fragments between station 0+420 and 0+500, mixed with medium dense sand and
silty sand layer between station 0+500 and 0+600. In those layers, the CPT cone
resistances qc were greater than 3 MPa. As a consequence, according
to the anticipated loads and subsequent design requirements, those layers were
able to be considered as suitably competent layers for the CMC. At certain
locations, a 1 or 2 m thick stiff clay layer (with qc>20 MPa) was
present at the bottom of the soft alluvium layer. Despite being stiff, the clay
layer was not considered as a suitable competent layer because of its limited
thickness.

Figure 3: CPT's performed along the embankment axis at
station 0+420 to 0+600
alternate
foundation systems
Three foundation systems considered for this project includes: conventional vertical (wick) drains, stone columns, and the CMC systems. “Time” was critical for this project, and thus a wick drain and surcharge solution was not acceptable to the project owners. Moreover, a CMC solution was preferred to a stone columns solution for the following reasons:
·
Predicted
settlement: The predicted settlement for stone columns was more than twice the
predicted settlement with CMC. The settlement requirement (less than 10 mm per
decade) was too strict to allow an economical solution using stone columns.
·
Field
performance: The alluvium layer was too soft to allow a safe implementation of
stone columns to support the embankment. The presence of critically soft clay
and peat, associated with high loading from the embankment (up to 155 kPa),
raised the possibility of bulging problems. Indeed, the very soft soil did not
provide enough lateral confinement to ensure the lateral stability of the stone
columns.
The ground improvement
solution takes into account the different loading conditions; the settlement
tolerance associated with those conditions; and the variability in different
soil characteristics. The CMC ground improvement was thus adapted from this
project. The design parameters needed to define the CMC reinforcement system
were:
·
The
depth of the columns and their possible anchorage length in the competent layer
·
The
diameter of the columns
·
The
pattern & configuration of the columns grids
·
The
modulus of the grout used to make the CMC. This parameter is adapted for each
new project, but for practical reason, is constant over a particular project.
The complete
design of the CMC includes estimation of bearing capacity of single columns, checking
pre-design parameters by a numerical procedure, stability analysis, and
development of final design, as discussed in the following sections.
The bearing capacity of a single CMC column was evaluated according to the equation of the ultimate capacity of piles in chalk proposed by Sanglerat (1972):
(1)
in which, k = 0.5; k1 = 0.5 (usually 0.5 < k1 < 0.9), A is the section of the CMC (0.138 m2 for diameter 420 mm, 0.101 m2 for diameter 360 mm); Z is the anchorage-length in the competent layer; and f is the diameter of the CMC. A factor of safety (FOS) of 2 was applied to evaluate the bearing capacity of the CMC’s.
The project was divided in two different areas, corresponding to the two main soil profiles of the site:
·
The
first case was the most general case (from station 0+460 to 0+600). In this
area, the thickness of the soft soil was less than 10 m, and anchorage-length
of 1.5 m were able to be executed. The stiff layer reached qc values
greater than 4 MPa, with a diameter of 360 mm, each CMC from this area was able
to support Qallowable = 185 kN/CMC. (taking into account a factor of
safety of 2)


Figure 4: Layout of the CMC
The CMC pattern could thus be estimated from those bearing capacities; simply by dividing them by the applied load. The result is the maximum area of influence that can be associated to one single CMC. For example: for an embankment of 5 m high the applied load was 5 m x 18 kN/m3 = 90 kN/m2 . In the general case (i.e., less than 10 m of soft soil), the area of influence of a single CMC was 185 kN/CMC / 90 kN/m2 = 2.06 m2/CMC corresponding to a square grid of 1.40 m x 1.40 m = 1.96 m2/CMC. The pattern of the ground improvement, depending on height of embankment and thickness of treated ground, is shown in figure 4.
To check this preliminary design, axial-symmetrical finite difference
method calculations have been implemented with the program PLAXIS. Under
uniform loads, the problem can be studied by an axial-symmetrical calculation
as shown in figure 5.

Figure 5 :Principle
of the axial-symmetrical calculation
This approach to the problem allows taking into account, under vertical loadings, the reinforced soil as well as the embankment, the geotextile (with ultimate tensile strength 84 kN/m and modulus 630 kN/m) and the transition layer. Thus it gives the strain and stress distribution between the soil and the columns. These FEM calculations were made in short term and long term conditions alike, in order to assess the time related behavior of the improved ground. For FEM calculation purposes, the parameters used in the numerical calculation for long-term behavior in correlation with available CPT’s cone resistance are shown in Table 1.
Table 1: Input parameters for FEM analysis
|
Material |
Alluvium |
Competent Layer |
Transition layer |
Embankment |
CMC
|
|
Modulus,E (MPa) |
1.5 |
15 |
35 |
80 |
11,000 |
|
Thickness (m) |
7.0
to 11.0 |
3.0 |
0.5 |
0 to 7.5 |
7.5 to 12.5 |
|
Cohesion (kN/m2) |
0 |
0 |
- |
0 |
- |
|
Friction Angle
(°) |
18 |
25 |
- |
33 |
- |
Note: a grout with unconfined compressive strength at 28
days fc28 greater than 11 MPa was chosen, the Young’s modulus of the
CMC was then assumed to be at least 11,000 Mpa.
For
short-term behavior, the geotechnical characteristics of the alluvium competent
layers were assessed using the following equation:
(2)
in which the short-term elastic modulus of 1.7 and 17 Mpa was adopted for the alluvium and stiff layers, respectively. To address all possibilities, two different cases, corresponding to the worst case scenarios, were studied:
|
Case 1: |
Case 2: |
|
· 7 m of soft soil |
|
|
· CMC diameter 360 mm |
|
|
· CMC mesh 1.40 m x 1.40 m |
|
|
· Embankment height (including transition layer): 5.00 m |
|
|
· Road surcharge: 20 kPa |
|
The main results of these axial-symmetrical FEM calculation are presented in Table 2.
The geotextile layer has been placed originally to increase the factor of safety against shear stress and was a requirement of the British Standard. However, the calculation showed that the tensile stresses in the geotextile were very limited.
The time related aspect of settlement was assessed by comparing the computed settlement for short and long term behavior. The difference between short and long-term settlement was of about 4 mm, and the typical duration for this settlement to occur was between 5 and 10 years to ensure that the settlement requirement of 10 mm per decade is respected.
Table 2 :
Results of numerical analysis

Note: The other cases with similar soft soil conditions
have been designed so that the load per CMC was comparable to the studied
cases.
Figure 6: Axial-symmetrical finite difference models, case 1 and 2
Stability calculation was performed using TALREN program to check possible slope failure problem during embankment construction. The results of these calculations showed a factor of safety against slip circle failure of 1.39.
Figure 7: Stability calculation
Due to very soft
ground condition for this project (particularly the
chalk layer), a very dense column spacing of 1.0 m square grid spacing was
initially adopted to correspond with
an area replacement ratio of 13.9 %. The area replacement ratios for CMC system are typically between 2 to 8 %, with CMC single columns designed to support loading of 150 to 350
kN. The
installation process use a displacement auger, and thus
the unusually high CMC density may have a risk of
damaging the freshly grouted surrounding columns during the installation of a
new CMC. Consequently, the conventional construction method was modified for the high
density area. The CMC columns were installed in two
different interleave passes, each with 1.4 m x 1.4 m
grids as shown in figure 8; corresponding
to an area replacement ratio of 6.9 %. The
CMC columns were anchored in the chalk or sand layers, resulting in columns in
length from
Figure
8: Modification of CMC layout
Construction challenges
The presence of
existing facilities imposed construction changes of the soil reinforcement
system in some areas. The main adaptation was related to the existing drainage
culvert at the site. This drainage culvert with a total width of about 2 m was
crossing the working area transversally. The requirement was to protect the existing
culvert against differential settlement. The decision was made to install
additional CMC to bridge the culvert and protect it. The strategy to reduce
differential settlement was to adapt the grid in order to have an almost
constant area of influence for each CMC even if the square pattern is modified
(see figure 9). With those construction changes, the predicted differential
settlement along the culvert was less than 3 mm, totally compatible with the
rigidity of the culvert.
Figure 9:
CMC grid modification along the culvert
Existing overhead
electrical cables were also crossing the construction site, requiring special
attention and safety measures. Equipment modification were also required in
order to shorten the mast of the CMC drilling rig to leave a safety distance
between the top of the rig and the live electrical cables, while still being
able to go to the required depths (see figure 10).
The quality of execution of each of those CMC columns was controlled
by monitoring and recording the followings for each individual column:
·
Speed
of rotation and advancement of the auger.
·
Torque,
down-thrust and drilling energy applied during advancement.
·
Pressure
and volume of injected grout, from which the profile of the columns are
determined.
The quality of the grout was controlled
regularly by unconfined compressive strength cube tests at 7, 14 and 28 days,
four cube samples for testing were taken every 100 m3 of grout. The
bearing capacity of the installed
CMC columns was controlled by the execution of 11 vertical load
tests on isolated columns (3 on CMC with diameter 420 mm and 8 on CMC with
diameter 360 mm). Those test were carried out until one-and-a-half times the
design load of the columns.

Figure 10:
Construction challenges near the culvert and the electrical cables
A complete settlement monitoring system including settlement plates and settlement pegs were installed over the treated area in order to record the potential settlement during and after construction of the embankment. The average settlement measured under the design loads of 185 kN and 153 kN was around 10 mm, equivalent to one third of the calculated settlement. However, the load test on an isolated CMC, in which only the CMC column is loaded, does not mobilize negative skin friction. Therefore, additional downward forces are induced by the differential settlement between the surrounding soil and the CMC column. As a difference, the uniform loading of the ground improvement system by the embankment does mobilize negative skin friction. These additional downward forces may result in additional settlement of the CMC columns.
The case history of the Tank Hill Road South Embankment project
demonstrates that CMC foundation system was an effective solution in timely
project delivery and meeting the serviceability requirements of the project.
The main challenges were associated with construction time limitation and very
soft ground condition of the site. In evaluating the alternatives stone column
was not feasible; and the conventional vertical drain solution was not
practical due to time constraints.
REFERENCES
Plomteux,
C. and Spaulding, C. (2003) Reinforcement of Soft Soils by Means of
Controlled Modulus Columns- 12th Pan-American Conference on Soil
Mechanics and Geotechnical Engineering –
Porbaha,
A., Brown, D., Macnab, A., Short, R. (2002a) Innovative European technologies
to accelerate construction of embankment foundations- part I: GEC, AuGeo, and
CFA. Proceedings of Time Factor in Design and Construction of Deep Foundations,
Deep Foundation Institute,
Porbaha,
A., Brown, D., Macnab, A., Short, R. (2002b) Innovative European technologies
to accelerate construction of embankment foundations- part II: DM, FMI, Mass
Stabilization, and CSV. Proceedings of Time Factor in Design and Construction
of Deep Foundations, Deep Foundation Institute,
Rogbeck, Y. & al. (1998) Two and three
dimensional numerical analysis of the performance of piled embankment, 6th
International Conference on Geosynthetics,
Rogbeck, Y. & al. (1998) Reinforced piled embankments in
Sanglerat, G. (1972) The Penetrometer and soil exploration Interpretation of penetration diagrams - Theory and Practice, Part 3 – Page 285.
Drainage & Ground
Improvement, Inc.,
Department
of Civil Engineering,
Charles
A. Spaulding
Menard
Soiltreatment, Inc. - 1331 Airport Freeway -